Retail construction is a three-player game — you, your builder, and a landlord with opinions. Win the paperwork early and the buildout is the easy part.
What's different here
“Vanilla shell” means whatever the lease says it means. Every item the landlord doesn't explicitly deliver is one you're buying. Have a GC price the gap between the work letter and your plans before you sign — we do this free, and it has killed some very bad leases.
Most leases give the landlord weeks to approve your drawings — a quiet schedule item almost every first-timer forgets. Submit early; nudge politely; repeat.
Malls and centers dictate work hours, barricades, sometimes approved contractors, and how your storefront may look. These rules are real costs; get them into the bid, not the surprises column.
Your sign needs landlord approval AND a separate city sign permit, and sign fabrication is long-lead. Nothing says ‘we slipped’ like a grand opening behind a blank fascia.
At multiple sites, consistency is the product: one prototype adapted per site, program-level purchasing, identical reporting. That's a program, not a stack of projects — and it's our favorite thing to run.
Timeline reality
In-line retail in a delivered vanilla shell moves quick; the schedule risks live almost entirely in paper — landlord review, permits, signage — not construction. The lever: get drawings to the landlord and the city in the same week, and order the sign the day it's approved.
The three mistakes
Terms you’ll meet on this one
When you're ready — or just curious
The expertise page has the process, the past projects, and a no-sales-call ballpark form. Or bring the 12 Questions and interview us properly — we like it.
Our Retail work The 12 Questions